1. The autoclave should be placed indoors. When equipped with multiple autoclaves, they should be placed separately. Each operation room should have an outlet directly leading to the outdoor or aisle, and the location of the equipment should be well ventilated.
2. When installing the kettle lid, the sealing surfaces between the kettle lid and the kettle lid should be prevented from bumping against each other. Place the kettle lid carefully on the kettle body at a fixed position. When tightening the main nut, it must be tightened diagonally and symmetrically several times. The force should be even and the kettle lid is not allowed to tilt to one side to achieve a good sealing effect.
3. Only the positive and negative nuts should be rotated at the joints of the positive and negative nuts. The two arc sealing surfaces must not be rotated relative to each other. When all the nut-shaped couplings are assembled, they should be coated with lubricating oil.
4. The needle valve line is sealed by turning the valve needle lightly and pressing the cover tightly to achieve a good sealing effect.
5. Move the rotary body on the kettle by hand to check whether the operation is flexible.
6. The controller should be placed flat on the operating table. Its working environment temperature is 10-40 ℃, relative humidity is less than 85%, and the surrounding medium does not contain conductive dust or corrosive gases.
7. Check whether the movable parts and fixed contacts on the panel and the rear panel are normal, remove the upper cover, and check whether the contact of the connector is loose, and whether there is damage or corrosion caused by improper transportation and storage.
8. The controller should be reliably grounded.
9. Connect all the wires, including the power wire, the electric furnace wire between the controller and the kettle, the motor wire, and the temperature sensor and speedometer wires.
10. Close the "power" air main switch on the panel, the digital display should show.
11. Set various parameters (such as upper limit alarm temperature, working temperature, etc.) on the digital display meter, then press the "heating" switch, the electric furnace is turned on, and the indicator light on the "heating" switch is on. Adjust the "pressure adjustment" knob to adjust the heating power of the electric furnace.
12. Press the "Stirring" switch, the stirring motor is energized, and the indicator light on the "Stirring" switch is on. Slowly turn the "Speed" knob to make the motor rotate slowly. Observe whether the motor is rotating forward. Belt and restart.
13. After the operation is completed, it can be naturally cooled, water-cooled or placed on the stand to be air-cooled. After the temperature drops, release the pressurized gas in the kettle to reduce the pressure to normal pressure (the pressure gauge shows zero), then loosen the main nut symmetrically and evenly, then remove the main nut, and then carefully remove the kettle cover Bracket.
14. After each operation, the residue on the kettle body and lid should be removed. The main sealing port should be cleaned frequently and kept clean, and it is not allowed to wipe with hard objects or rough surfaces.